Court filings show what ICE agreed to buy now, what would require another federal decision and why New Jersey and Roxbury may ask a judge to intervene.
ROXBURY, NJ – U.S. Immigration and Customs Enforcement has committed $31.8 million to maintain its warehouse at 1879 Route 46, design a facility that could hold immigration detainees and assess the environmental effects of that design. The contract, filed in federal court Nov. 17, would reach $998.3 million if ICE exercises all of its options, including a full retrofit and five years of operations.
Roxbury officials had been asking what work the federal government hired a contractor to do. On Nov. 16, Mayor Shawn Potillo and the Township Council made public a statement from U.S. Sen. Andy Kim saying his office had asked Homeland Security to explain the award.
ICE signed the order with SK2 LLC on Nov. 5. Of the money committed, $650,000 pays for environmental review. The other $31,127,231 covers four months of maintenance and repairs along with design work. ICE’s preferred design would provide some detention capacity and could also include training and office space, according to Sarah West, the agency’s contracting officer.
The largest construction item is still optional. West identified $206.5 million for a full retrofit and said ICE had committed no money to that work. The same was true of the contract items for detention operations and transporting detainees. She said ICE could exercise those options only after completing the required environmental analysis and issuing a decision.
What the judge’s order allows
New Jersey and Roxbury sued over the proposed conversion in March, raising concerns that a detention center would strain local water and sewer systems. A May 12 order, signed by U.S. District Judge Jamel K. Semper, allows the federal government to secure and maintain the property. It restricts work at the site to convert it into a detention center until the agencies complete an environmental assessment, issue a decision and give the plaintiffs an opportunity to seek court review.
The contract draws a distinction that could matter if the parties return to court. Its work terms allow the government to approve some interior work on administrative offices while environmental review is underway. Renovations to house detainees must wait. The May order lists permitted security and maintenance activities, including changing locks and servicing building systems. The documents give no start date for office construction in Roxbury.
The procurement also predates ICE’s public acknowledgment that it intended to retain the building. SK2’s offer was dated Sept. 4. In a Sept. 15 court filing, federal officials said they were still considering whether to convert the warehouse and had no timetable for a decision. Project Salt Box first reported the procurement timeline from the newly filed records.
In a Nov. 18 House Homeland Security Committee hearing, Rep. Analilia Mejia, whose district includes Roxbury, questioned Homeland Security Secretary Markwayne Mullin about the award. Mullin said full construction had not begun and described the project as still in bidding. Asked if the environmental review was complete, he said he did not know. The contract filed the day before identifies the design work ICE had already awarded.
New Jersey and Roxbury told Semper they had received 178 pages of contract records on Nov. 17 after seeking them for 11 days. They said they would review the documents before deciding whether to ask him to enforce the May order. Federal lawyers told the judge the contract complies with the order and proposed another status report on Jan. 15, 2027. Neither side asked him to set a hearing on a renewed injunction at that point.