The state and township want construction funds canceled while ICE reviews the environmental impact. Federal lawyers say the money committed so far pays for design, maintenance and the review itself.
ROXBURY, NJ – New Jersey and Roxbury Township asked a federal judge Nov. 23 to bar construction at the proposed immigration detention facility at 1879 Route 46, cancel any money committed to construction and allow state and local officials to inspect the property. The motion reported by the New Jersey Globe asks U.S. District Judge Jamel K. Semper to enforce an agreement he approved in May.
The immediate dispute is over work that U.S. Immigration and Customs Enforcement can authorize while it evaluates the site. In their March lawsuit, the state and township questioned whether the warehouse had sufficient water and sewer capacity for a facility that could hold up to 1,500 detainees. An environmental assessment would give them a record against which to test the federal government’s conclusions.
Under the May 12 order, ICE agreed to complete an initial assessment, decide what to do with the warehouse and give the plaintiffs an opportunity to challenge that decision before converting it. The agreement allowed the government to secure and maintain the property. The state and township argued in their Nov. 19 letter to the judge that awarding a contract to prepare the facility for detention commits the government to a course of action before it has finished the review.
What ICE has agreed to buy
ICE awarded the contract to SK2 LLC on Nov. 5. Sarah A. West, the agency’s contracting officer, told the court under oath that ICE committed $31.8 million. Of that, $650,000 pays for the environmental review. The other $31.1 million covers four months of maintenance and repairs, along with design work for possible detention, training and office uses. The contract could reach $998.3 million if ICE exercises all its options, including five years of operations, as Morristown Minute previously reported.
West’s declaration identifies an important distinction in the contract. The government can give a contractor permission to reconfigure administrative or office space during the review. Renovations to house detainees require an environmental finding first. In a Nov. 20 filing, Justice Department attorneys said ICE had committed no money to housing renovations and had complied with the May order.
The inspection request would give New Jersey and Roxbury a way to check what is actually happening inside the warehouse. Semper’s decision on the enforcement motion would determine whether ICE faces additional restrictions while the environmental review proceeds.